This was our last week with Wieser Brothers onsite, so this is their last status report. We really appreciate that they made these reports for us. It made it super easy for us to keep everyone informed.
Read MoreExpansion Updates
Tags: Expansion
The countdown has already begun. After we pass state inspection tests, we get to start firing up our new Deli equipment to see how it all runs! Believe it or not but the Deli counter may even be up and running by the end of next week!
Take a look below, or come on in. #wecantwait #almostthere #todayatthecoop
Read MoreTags: Expansion
Deli equipment installation continues this week. The Deli counter, cabinets and cases are moved into place. Take a look below, or come on in.
Read MoreTags: Expansion
It is now possible to see the future deli area, as the plastic wall is down. There is a lot of equipment being prepared for installation, and behind the deli wall sinks are being plumbed.
Read MoreTags: Expansion
Tags: Expansion
UPDATE: The last day of the Taco Truck is next week Wednesday (9/5/18). You know why? Because our Deli staff is preparing as this last expansion phase is really starting to take shape!
Have you checked out the kitchen flooring and wall tile yet? It's now visible and looking impressively close to complete! Stop in to see all the progress and get equally excited for us to cross the finish line of this project...
#wecantwait
#wearesoooooclose
#todayatthecoop
Tags: Expansion
It's hard to see the progress behind the scenes when you are in the store, but here's a peek. Kitchen hoods, freezer & cooler were installed in the deli area. Something you CAN see is the monument sign on Main Street. It doesn't have any letters on it yet, but eventually it will have the same lit-from-inside lettering that's on the parking lot signs. Coming this week is the flooring process, which will take a couple weeks.
Read MoreTags: Expansion
ATTENTION: We're closing at 5:30pm this Wednesday.
This is to assist with some behind-the-scenes expansion stuff and allows our Board of Directors the opportunity to host a VFC Staff Party as we near the finish line of the expansion project.
Check out what the construction crew has been able to accomplish in the last week by clicking the image below!
Read MoreTags: Expansion
Our parking lot is finished, drive on in! The kitchen is taking shape with walls going up.
The fabulous Taco Truck moved onto our new patio and there is more comfortable seating in the shade.
Taco Truck Mon-Sat (Hours are: 11am-2:30pm & 4pm-7pm)
Read MoreTags: Expansion
The kitchen floor is down, but walls are going up, so thanks for your continued patience as we make more noise. We are working around weather but so very close to parking lot completion.
Come to see the great new products as we continue to fill the shelves; stay for a taco!
Taco Truck in the parking lot Mon-Sat (Hours are: 11am-2:30pm & 4pm-7pm)
Read MoreTags: Expansion