Expansion Updates

EXPANSION UPDATE: October 13, 2016

Posted by VFC Marketing Team on Oct 13, 2016 3:45:00 PM

Brief Update

10-12_for_web.jpg

For the following ~3.5 weeks, we asked our staff to refrain from parking within 1-2 blocks from the store to ensure our customers can park as close as possible.

Weather permitting, we’re on track to finishing about 3/4 of the new parking lot by the first week of November. Should go something like this:

  • 10-12-16: Site Layout & Staking – 1 day
  • 10-12 to 10-13: Electrical Underground – 2 days

  • 10-13 (potential rain delay): Tree Spade moves 3 trees – 1 day

  • 10-13 to 10-14: Gravel Parking Lot – 2 days

  • 10-17 to 10-18: Concrete Curb & Gutter – 2 days 

  • 10-19 to 10-25: Concrete Paving – 5 days 

  • 10-31 to 11-1: Light Pole Bases – 2 days 

  • 10-31 to 11-1: Landscaping along east lot line – 2 days 

When the concrete has cured enough, we will stripe and be able to use about 3/4 of the new lot.
Whoo hoo! This will give us more spaces than the old east lot. The remaining parking lot construction will be finished in the summer of 2017. 

Thank you for your patience!

Tags: 2016, Expansion